In service · HVAC · subsea
Crete–Peloponnese Interconnection
The first power link between Crete and mainland Greece, and a record for alternating-current cable length at completion.
Route drawn between the landing points; outlines: Natural Earth.
- Route
- within Greece
- From
- Chania, Crete
- To
- Molaoi, Peloponnese
- Length
- 174 km
- Of which subsea
- 132 km
- Capacity
- 400 MW
- Voltage
- 150 kV
- Type
- HVAC · subsea and land cable
- Status
- In service (checked September 2026)
- In service since
- 2021
- Operators
- IPTO
- Built by
- Nexans; Hellenic Cables
Engineers usually switch to direct current when a sea cable gets long, because an AC cable loses more and more of its capacity to charging current with distance. The Crete–Peloponnese link pushed that limit. At 174 km, running at 150 kV AC, it was on completion the longest submarine and underground AC cable interconnection in the world, according to IPTO, which built it.
IPTO announced completion on 20 May 2021. The route lands at Chania, on the western end of Crete, and at Neapoli in Laconia, at the tip of the south-eastern Peloponnese. At its deepest the cable lies 1,000 metres down. There are two circuits, each rated at 200 MVA, given above as 400 MW. Nexans and Hellenic Cables supplied the cables, and the whole project cost €380 million, co-financed by Greece, the EU and European Investment Bank loans.
The job it was given was a first step. IPTO said the link would cover about a third of Crete’s demand, which on its own would not let the island close its local plants. The savings came from the public service charge that all Greek consumers pay towards the cost of generating power on unconnected islands: IPTO estimated reductions of up to €400 million a year once the old plants could be shut down.
“The future of Greece’s energy transition passes through the sea,” Manousakis said at the time. Energy minister Kostas Skrekas called it a project “of the utmost importance for the whole country, especially for Crete”.
The full connection arrived four years later, in May 2025, with the 1,000 MW Crete–Attica link, a DC cable from Heraklion to Attica. IPTO’s 2021 announcement had aimed for 2023. The Peloponnese cable remains the western, AC half of Crete’s two-cable supply, and for anyone studying subsea power cables it is a useful case of how far an AC design can be stretched.
Against the other links
- 36th longest of the 54 links with a published length; the longest is Tyrrhenian Link at 970 km.
- 54th largest by capacity of 60; SuedLink leads with 4,000 MW.
Crete–Peloponnese Interconnection in brief
How long is Crete–Peloponnese Interconnection?
174 km, of which 132 km under the sea, which makes it the 36th longest of the 54 links in this directory with a published length.
How much power can Crete–Peloponnese Interconnection carry?
400 MW at 150 kV, 54th of 60 by capacity here.
When did Crete–Peloponnese Interconnection open?
Crete–Peloponnese Interconnection entered service in 2021.
Which countries does Crete–Peloponnese Interconnection connect?
It runs within Greece, from Chania, Crete to Molaoi, Peloponnese.
Who operates Crete–Peloponnese Interconnection?
IPTO.
Who built Crete–Peloponnese Interconnection?
Nexans; Hellenic Cables.