In service · HVDC · subsea
Viking Link
The longest land and subsea HVDC interconnector in the world when it opened, linking Lincolnshire with southern Jutland.
Route © OpenStreetMap contributors; outlines: Natural Earth.
- Route
- Great Britain to Denmark
- From
- Bicker Fen, Lincolnshire
- To
- Revsing, South Jutland
- Length
- 765 km
- Of which subsea
- 650 km
- Capacity
- 1,400 MW
- Voltage
- 525 kV
- Type
- HVDC · VSC · subsea and land cable
- Status
- In service (checked September 2026)
- In service since
- 2023
- Operators
- National Grid, Energinet
- Built by
- Siemens Energy (converters); Prysmian and NKT (cable)
Eighty per cent of the time, Viking Link carries power from Denmark to Britain. That is the headline from the operating data summarised in the Viking Link article: in the first quarter of 2024 the cable moved 1,733 GWh at a 55% capacity factor, and the two owners had earned about €20 million between them.
The route is long even by North Sea standards. From the converter station at Bicker Fen in Lincolnshire, the link runs 765 km to Revsing in southern Jutland, 650 km of it under the sea. When it opened it was the longest land and subsea HVDC interconnector in the world. The cable itself, made of copper, steel, paper and plastic, weighs about 40 kg per metre.
Construction started in 2019. Land and submarine cables went in between 2020 and 2023, and the undersea section was completed in July 2023. National Grid and Energinet began commercial operation on 29 December 2023, but at 800 MW only, because the Danish grid behind Revsing was not yet ready to carry the full rating. From January 2024 the link could reach its 1,400 MW design capacity under certain conditions. Siemens Energy supplied the 525 kV voltage-source converters, and Prysmian and NKT supplied the cable.
The first fault came quickly. In February 2024 a minor fire in a switching station at Revsing took the link out of service. After four years of work at sea, the first outage started in a building on land.
Viking Link was built as a PCI, a Project of Common Interest in EU terms, to give the two markets a direct route to each other for the first time. The early flows show which side needed it more in 2024: Denmark exported most of the time.
The published lengths differ by two kilometres: 765 km in National Grid’s announcement and 767 km in Siemens’ order announcement. This page gives 765 km. For the other long North Sea links, see North Sea Link and the guide to subsea power cables.
Against the other links
- 3rd longest of the 54 links with a published length; the longest is Tyrrhenian Link at 970 km.
- 17th largest by capacity of 60; SuedLink leads with 4,000 MW.
- Other links from the same countries: AQUIND Interconnector, Bornholm Energy Island, BritNed, Caithness–Moray HVDC Link, East–West Interconnector, Eastern Green Link 1, Eastern Green Link 2, ElecLink and 16 more.
Viking Link in brief
How long is Viking Link?
765 km, of which 650 km under the sea, which makes it the 3rd longest of the 54 links in this directory with a published length.
How much power can Viking Link carry?
1,400 MW at 525 kV, 17th of 60 by capacity here.
When did Viking Link open?
Viking Link entered service in 2023.
Which countries does Viking Link connect?
Great Britain and Denmark: Bicker Fen, Lincolnshire to Revsing, South Jutland.
Who operates Viking Link?
National Grid and Energinet.
Who built Viking Link?
Siemens Energy (converters); Prysmian and NKT (cable).