Best Paths

In service · HVDC · subsea

Italy–Greece HVDC (GRITA)

The only direct power link between Italy and Greece, a monopole cable under the Strait of Otranto.

Route © OpenStreetMap contributors; outlines: Natural Earth.

Route
Italy to Greece
From
Galatina, Apulia
To
Arachthos, Epirus
Length
310 km
Of which subsea
160 km
Capacity
500 MW
Voltage
400 kV
Type
HVDC · LCC · subsea and land cable
Status
In service (checked September 2026)
In service since
2001
Operators
Terna, IPTO
Built by
ABB (cable)

On 18 May 2021 the only cable between Italy and Greece failed. The allocation office for cross-border capacity, JAO, cut the available capacity to zero and curtailed long-term rights already sold, and JAO’s notices show the outage running well into the summer while crews found further damage caused by third parties. For weeks, Greece and Italy had no direct way to trade electricity.

The link itself dates from 2001. It starts at the converter station at Galatina, in the Salento peninsula of Apulia, runs about 40 km underground to the coast near Otranto, and crosses the Ionian Sea by a 160 km submarine cable. It lands on the Greek coast at Aetos, south of the Albanian border, and continues 110 km as an overhead line to the Arachthos converter station in Epirus. The Wikipedia article on the link gives these sections; other sources give slightly different totals, and this page gives 313 km.

It is a monopole: one 400 kV conductor, with the current returning through the sea. The electrodes sit at each end, a bare copper cathode on the Italian side and an anode in a bay on the Greek side. ABB made the cable. The operators are Terna in Italy and IPTO, the successor to the Greek operator HTSO.

At 500 MW, it is small by current standards, and a single fault removes the whole border.

That is the argument for a second cable. Terna and IPTO have been working on GR.ITA 2, which would land at Melendugno on the Adriatic coast of Apulia and at Thesprotia in Greece, across from the southern tip of Corfu. Balkan Green Energy News reports a subsea section of about 250 km, a 50 km underground AC run to Galatina, and two HVDC cables adding 1 GW, which would take the border to 1.5 GW. The expected cost there is €750 million, and Terna held a public consultation with seven municipalities in the province of Lecce. No construction date has been fixed.

Against the other links

Italy–Greece HVDC (GRITA) in brief

How long is Italy–Greece HVDC (GRITA)?

310 km, of which 160 km under the sea, which makes it the 20th longest of the 54 links in this directory with a published length.

How much power can Italy–Greece HVDC (GRITA) carry?

500 MW at 400 kV, 50th of 60 by capacity here.

When did Italy–Greece HVDC (GRITA) open?

Italy–Greece HVDC (GRITA) entered service in 2001.

Which countries does Italy–Greece HVDC (GRITA) connect?

Italy and Greece: Galatina, Apulia to Arachthos, Epirus.

Who operates Italy–Greece HVDC (GRITA)?

Terna and IPTO.

Who built Italy–Greece HVDC (GRITA)?

ABB (cable).

Background reading

  1. GuideSubsea power cables: how installation, protection and repair work on the seabed
  2. Direct currentHVDC transmission explained: the cable, the converter station and why DC wins

Nearby links

  1. MONITA (Italy–Montenegro)Italy to Montenegro · 600 MW · In service
  2. Crete–Peloponnese Interconnectionwithin Greece · 400 MW · In service
  3. Crete–Attica Interconnection (Ariadne)within Greece · 1,000 MW · In service
  4. Malta–Sicily InterconnectorMalta to Italy · 200 MW · In service

All power links on the map